mted machinery logo

How to Install and Commission a Foil Container Machine

A foil container machine is installed and commissioned in ten steps on the buyer’s floor: prepare the foundation and utilities, receive and set the press, level and anchor it, connect air, power and oil, set up the line units around it, prove the safety devices, run it empty, fit the mould, run it with foil, and sign it off. Installation puts the line in place and connects it; commissioning proves that the connected line makes good containers at speed.

Step 1: Prepare the Floor and Utilities

Before the line arrives, the foundation must be built to the press maker’s drawing and air and power must be brought to the machine position. That site work is the buyer’s: the supplier sends the foundation drawing, the general assembly drawing and the utility requirements, and your contractor builds to them. The supplier’s engineer then installs and commissions the line on your floor.

Floor and Foundation

The press needs the foundation shown on its maker’s drawing, because no single floor thickness suits every press.

Give the foundation contractor the press drawings, the press weight and a soil report before they pour. An MTED H-type press weighs 11,350 kg for the RZLH-H63T and 13,950 kg for the RZLH-H80T, and it stands on shock pads.

Press foundations are usually poured in two stages. The pit is cast with pockets left for the anchor bolts, the press is set and levelled with its bolts and levelling plates in those pockets, and only then are the pockets grouted. The floor plates around the machine are also the buyer’s to fill.

Air and Power at the Machine Position

MTED’s C-type and H-type presses both need compressed air at 0.55 MPa (about 80 psi) at the machine. Measure that at the machine inlet, after the filter, regulator and hose, because a filter, regulator and hose together typically drop about 7 psi, and more on a badly kept system. The plant supply has to be set high enough to cover that drop.

The C-type press runs on 380 V, 3-phase power, with a 7.5 kW main motor; the H-type models carry 11 kW or 18.5 kW drives. 380 V is a standard 50 Hz supply voltage and not a North American 60 Hz one, so a plant on a North American 60 Hz grid does not have it at the wall. Settle that with the supplier before the machine ships, either with a transformer or with motors and controls built for your supply.

Step 2: Unload, Inspect and Position the Press

The press is checked for transit damage and missing parts as it comes off the truck, lifted onto its foundation with slings, and then has the parts removed for shipping refitted.

Receiving Inspection

Check the outside of every crate and machine for damage before you sign for the delivery, and report any damage to both the supplier and the carrier. Then check the standard and special accessories against the packing list, and report anything missing the same way.

Lifting and Rigging

Lift the press with rated wire rope slings, not chains, rigged to the lifting points the maker specifies. Check the rope surface for damage first, and pad the rope where it bends over a corner of the frame.

OSHA’s sling guidance sets the horizontal angle of each sling leg at no less than 30 degrees unless the sling maker or a qualified person allows otherwise. Raise the press just clear of the floor, check that it hangs level, and only then lift it over the foundation.

Set the press down over the anchor-bolt pockets without tilting it backwards. If the press has to be moved by hand, pull it; never push it.

Refit Parts Shipped Loose

The parts usually shipped loose are the main drive motor and its V-belts. Support the motor on a sling while its bolts go in, align the motor sheave with the flywheel groove, then fit and tension the belts to the press maker’s own figure; Kinglan’s is about 1/2 inch of deflection under thumb pressure.

Two cleaning jobs come with the refit. Wipe off the anti-rust oil applied for transport, especially on the gibs and sliding surfaces, and keep the contact faces clean if the bolster or working table is fitted on site.

Step 3: Level and Anchor the Press

Level the press on its bolster, shim it to the tolerance in its own manual, and only then tighten and grout the anchor bolts. Lock and clean the bolster first, then place a precision level on it at the front, middle and back, reading both front to back and left to right.

Correct low corners with shims or levelling plates at least as large as the press foot. Neither MTED product page publishes a levelling tolerance, and press makers’ figures differ: Kinglan levels to within 0.1 mm, and one JH21-80T press manual requires 0.3 mm per 1,000 mm before the foundation bolts may be fixed. Use the figure your press manual gives.

Step 4: Connect Air, Power and Lubrication

Air, power and oil are all connected and checked with the press still locked out, and nothing turns until all three are in.

Compressed Air

Take the press’s air drop off the top of the main line, run the machine outlet off the side of the drop, and fit a drain at the bottom. The air must reach the clutch and brake valves through a filter and regulator, with a lubricator where the valve maker requires one.

Blow the new line clean before connecting it to the machine. Then pressurise it slowly, opening the valves one circuit at a time, and check every joint, the clutch cylinder and the rotary union for leaks.

Leave the factory-sealed regulator alone; only the supplier’s engineer should break the seal to reset it.

Electrical Connection

Isolate the supply with the main disconnect, which on a mechanical power press must be lockable only in the Off position, and connect the incoming cable to the control box terminals as the wiring diagram shows. Earth the frame.

Check the incoming voltage before first power-on. NEMA allows a motor ±10 % on voltage and ±5 % on frequency.

Jog the main motor to check its direction of rotation against the direction marked on the press. If it runs backwards, swap two incoming phases at the point the maker’s terminal instructions name, since some control transformers take their supply from one specific phase that must not be moved.

Oil Fill

Fill every reservoir and grease every point on the press’s lubrication chart before the first run. On a crank press that means the connecting rod and main bushings, the gibs, the gearbox, the slide-adjustment screw, the flywheel bearing and the air-line lubricator, each with the grade the maker’s chart names.

Keep oil and grease off the friction surfaces of the clutch and brake. Release the air pressure before topping up the air-line lubricator. After the first run, check levels as described in how to check oil levels in a foil container machine.

Step 5: Set Up the Decoiler, Feeder, Oiler and Stacker

The units around the press are placed on the press’s feed centreline and timed to its stroke.

Decoiler and Coil Loading

Place the decoiler in line with the feeder and the press centreline, far enough back that the foil forms a slack loop before the oiler and feeder. Load the first coil so that it unwinds in the direction the feeder takes it, without twisting the strip, and thread it through the oiler into the feeder by hand with the press locked out.

Feeder Height and Pitch

Mount the feeder rigidly and square to the mould, then set its feed line height to the level at which the foil enters the mould.

Set the feed pitch to the mould’s pitch and the stock guides wide enough to pass the coil’s natural camber. Feed the first strip up to the mould’s starting mark.

Oiling Unit

Set the oiling unit to coat the whole width the mould draws, close any manifold zones that would coat foil the mould never touches, and start lean. The unit meters lubricant onto rollers that spread an even film across the foil, top and bottom if required. Take the oil type and quantity from lubrication requirements for aluminum foil deep drawing.

Air Ejection and Stacker

Time the air ejection blast to the top of the stroke, after the mould opens and before the next feed, so it blows each formed container out of the mould cavity and onto the stacker. Set the stacker for single-track or multi-track collection to match the mould’s cavities, and set the counter to the stack count your packing uses. Route the skeleton scrap away from the operator.

Step 6: Check the Safety Devices

Before the press makes a single powered stroke, prove the stop controls, the mode selector, the clutch’s response to loss of air and every guard interlock. MTED’s presses are crank presses with a pneumatic clutch and brake, so in the US they come under OSHA 1910.217 for mechanical power presses, and internationally under ISO 16092-2.

  • Red stop and emergency stop: a momentary press must disengage the clutch and apply the brake at once.
  • Mode selector: Off, Inch, Single Stroke and Continuous must each do only what they say.
  • Loss of air: cutting the clutch air supply must deactivate the clutch control.
  • Guard interlocks: the clutch must not engage with any movable guard section open.
  • Main disconnect: it must lock in Off and nowhere else.

Agree lockout procedures with the supplier’s engineer before work starts. Under lockout, stored air in the lines and receiver is bled off, not just shut in.

Step 7: Run the Press Without Load

The no-load run proves the press strokes, stops and repeats correctly with no mould and no foil in it. Clear tools and people from the press, remove the locks in the order your lockout procedure sets, and start the main motor, letting the lubrication pump run before the first stroke.

Check that the clutch air gauge reads its rated pressure, the clutch and brake solenoid valves act, and nothing leaks. Then work through the modes: inching must move the slide smoothly, a single stroke must stop at top dead centre and not repeat while the button is held, and the emergency stop must stop the slide immediately. Kinglan accepts a top-dead-centre stop within ±15° on its presses; your press manual gives its own figure.

Finish with a spell of continuous strokes, listening for knocks and checking for leaks again.

Step 8: Install and Align the Mould

The mould is set on the press centreline, aligned parallel to the feeder, and closed for the first time with the shut height set above the mould height. Clean both mould halves, the bolster and the slide face first.

Centre the mould left to right on the press centreline. Key it or stop it against the bolster so it sits parallel to the feeder. Raise the shut height above the closed mould height before lowering the slide, and never set the final shut height while the mould is empty.

Fix the upper half to the slide and leave the lower half’s bolts loose. Inch the press down a few times so the lower half centres itself on the upper, then tighten the lower bolts with the mould nearly closed, using every clamping slot. Use safety blocks whenever anyone adjusts the mould in the press.

Step 9: Trial Run With Foil

The first run with foil starts at inching speed on your own production foil and ends with containers that meet the agreed specification at the line’s synchronized speed of 40 to 80 strokes per minute. Inch the first strokes, removing loose scrap after each one.

Set the final shut height now, with foil in the mould. Lower it in small steps until the container forms fully at the flange and corners, and stop there.

Check the first containers against the drawing or sample agreed in the purchase contract: depth, flange, wall finish and freedom from wrinkles, cracks, pinholes and burrs. Then raise the speed in steps toward production speed and check again, because a change in press speed shifts the shut height the mould needs. Causes of defects that appear here are covered in foil container quality control.

Step 10: Sign Off and Hand Over

Commissioning ends with a completion acceptance certificate signed by both buyer and supplier, plus a punch list of any work still incomplete or not working, each item with an owner and a date. With it come the documents your plant will run on: the manuals, the wiring and lubrication charts and the supplier’s start-up procedure.

Train operators and maintenance staff before you sign, while the supplier’s engineer is still on site; the operator training programme is a separate job. Recheck the press level and the anchor bolts after the first month of production, and the V-belt tension after the first few days.