How to Increase Foil Container Production Capacity on an Existing Line

An existing foil container line produces more containers per hour when you raise one of three numbers: strokes per minute, containers per stroke, or the minutes the press actually stamps. Cutting scrap then turns more of those strokes into good containers.

Start by comparing the line’s actual daily count with its rated production capacity. A line that runs near its rated speed but still falls short is losing time to stops, changeovers and scrap. A line that cannot hold its rated speed has a station holding the press back.

Find the Station That Sets the Line Speed

The station that sets the line speed is the slowest of feeding, oiling, stamping, air ejection, stacking and counting.

To find it, log every stop and every delayed stroke by station over a full shift at the set speed. The station that appears most often is the first one to fix.

On many lines that station is a manual one: an operator stacking and counting by hand, clearing the foil skeleton, or carrying scrap away. Automating that step raises output without touching the press. Fix the slow station before raising stroke rate.

Run the Press Faster

Stroke rate on an existing container press can be raised up to the line’s synchronized rating, and only as far as feeding, oiling, ejection and stacking still finish inside each stroke. The true synchronized line speed of an MTED C-type container line is 40–80 strokes per minute, and that range is the figure to plan capacity against.

If your line already runs inside its rating and the count still falls short, more speed is rarely the fix. Raise speed in small steps and re-set feed and air-ejection timing at each one. Hold each step long enough to count good containers, and stop at the last step where that count still rises. That step is the line’s stable speed, and it is the speed to run.

Add Cavities to the Mould

A mould with more cavities raises output on the same press when the press has the tonnage, table size, foil width and stacker tracks to take it.

One maker, Bescomt, ties cavity count to line size in its selection guide:

Bescomt lineCavities per strokeFeeder widthCollector tracks
45-ton2 for containers up to 1,000 ml; 1 for 1,000–2,500 ml600 mm2
63-ton2 for containers above 1,000 ml; 3 for small containers900 mm3
80-ton gantry4 or 5 for containers above 750 ml1,300 mm4

Before ordering a bigger mould, check your press’s tonnage, table size, maximum foil width and stacker tracks against that guide.

The frame is the last check. An open-back C-frame deflects under very large multi-cavity moulds and deep draws, and MTED puts those moulds on its closed H-type gantry press.

Cut Mould Change Time

Mould change time is shortened by doing every task that can be done while the press is still running before you stop it, and by removing the adjustments and loose tools the stop itself needs:

  • Prestage the next change: bring the next mould, clamps, tools, foil coil and lubricant to the press while the current mould is still running.
  • Standardise mould heights: spacer plates give every mould the same shut height and feed line height, so neither is reset at each change.
  • Clamp without tools: quick or hydraulic clamps replace bolts that have to be found, loosened and torqued.
  • Support the mould on the way in and out: bolster extension arms let the mould roll in and out of the press instead of being lifted.
  • Keep tools and moulds in one place: one storage point for hand tools beside the press, and mould storage the operator can reach without searching.

Measure your current mould change from last good container to first good container.

Cut Coil Change Time

Foil coil change time is shortened by preparing the next coil before the current one runs out, and by changing coils less often:

  • Prestage the next coil: have it mounted on its shaft and waiting at the decoiler with the lift ready, so the stop covers only unloading, loading and threading.
  • Change the coil with the mould: when a mould change is due and the coil is nearly finished, do both in the same stop.
  • Run heavier coils: a heavier coil makes more containers per change, up to the weight your decoiler and your crane or forklift can handle.
  • Add a second mandrel: a double-mandrel decoiler loads the next coil while the first one feeds the press, at the cost of more floor space.

Time your current coil change before deciding whether a second mandrel pays.

Cut Unplanned Stops

The unplanned stops that cost the most output are the ones that add up to the most minutes, and on press lines two causes often lead: scrap caught in the machine and mould repairs.

On a foil container line, stuck scrap means a torn or snagged skeleton, or containers left on the mould when ejection misses. Both are prevented by keeping the scrap winder or waste collector and the ejection air sized for the stroke rate, and by re-setting them whenever speed or cavity count changes.

Mould repairs are prevented by maintaining moulds on a stroke count before they fail. Keep a spare of the mould that runs the most hours, so a repair stop takes only as long as a mould change. Log every stop by cause and duration, and work on the cause with the most minutes first.

Cut Scrap to Raise Good Output

Every scrapped container used a stroke, foil and press time, so cutting scrap raises good containers per hour by the same share, at the same speed, cavity count and running time. Count capacity at the end of the line:

Good containers per hour = containers formed per hour × (good containers ÷ all containers formed)

Some scrap arrives in the coil. If pinholes rise with a new coil or supplier, check the incoming foil before adjusting the mould.

Other scrap comes from one forming step. Sort rejects by defect and by where on the container each one sits: the location points to the forming step, or to the coil, that made it.