Foil Container Machine Factory Acceptance Test: What to Check

At the factory acceptance test (FAT) of a foil container machine, you check two things before the line leaves the builder’s floor: that it is built, wired and guarded as the contract says, and that it makes your containers from your own foil at the contracted line speed.

A FAT cannot prove anything that depends on your plant. Your power supply, compressed air and the equipment before and after the line are tested at the site acceptance test (SAT) after installation.

Agree the acceptance criteria in writing before the test day: line speed, run quantity, the container drawing with its tolerances, and the changeover time. Send the person who will run the line, plus someone with authority to sign the FAT report.

Static Checks Before Power-On

Before power-on, inspect the line’s scope against the contract, its mechanical build, its electrical cabinet and its safety devices.

Scope Against the Contract

Walk the line unit by unit with the contract’s equipment list and confirm that each unit is there, is the model the contract names, and carries a nameplate whose serial number you record. On a foil container line the units are the decoiler, feeder, oiler, press, mould, air ejection and stacker-counter.

For each mould, check the cavity count and the container drawing number against the contract. Where the contract names brands for bought-in parts such as the PLC, servo drives or air valves, read the brand on the part itself. A substitution may be reasonable, but it is yours to approve.

Mechanical Build and Lubrication

With the power off, check the fasteners, mould mounting, strip alignment, lubrication and compressed-air fittings, the items that cause trouble first on a new line:

  • Fasteners: no missing or loose bolts on the press frame, mould clamps, decoiler and feeder; tightened bolts carry a torque mark.
  • Mould mounting: both halves of the mould seated and clamped, guide posts clean and oiled.
  • Strip line: decoiler, feeder and press on one centre line, so the foil strip enters the mould straight.
  • Lubrication: the press lubrication reservoir filled with the oil grade the manual names and a line connected to every point; the foil oiler filled with the stamping oil you will use in production.
  • Compressed air: with air connected and the motor off, no audible leaks at fittings, valves or cylinders.

Electrical and Controls

Open the electrical cabinet with the electrical schematics in hand and check it against them:

  • Wiring: wire numbers and terminal labels match the schematics.
  • Earthing: every unit, including the decoiler and stacker, is connected to protective earth.
  • Cable routing: cables run in trays or conduit, clear of foil edges and moving parts.

Ask which standard the electrical equipment is built to. The usual one is IEC 60204-1, adopted in Europe as EN 60204-1.

Safety Functions

With the power off, confirm that the safety devices are present and placed where operators work. The first act after power-on, before any running, is to trip each one and watch the press stop.

  • Die-area guarding: the mould area is closed by fixed guards, interlocking guards or protective devices such as light curtains; a guard you open in normal work, such as for a mould change, should be interlocked so that opening it stops the press.
  • Emergency stops: one within reach at each operator position, at least at the decoiler, press and stacker; pressing one stops the line, and it stays latched until it is deliberately released.
  • Energy isolation: a main isolator that can be locked in the off position, and a way to vent the compressed air left in the lines after the supply is shut.

The general press-safety standard to ask the builder about is ISO 16092-1.

Running Tests

With power on, the line is run empty first, then on your own foil while the containers are measured, then through a timed mould change and a set of deliberate faults.

A remote or video FAT can show that the line runs, but through a camera you cannot measure containers, count output or choose which faults to trip.

Dry Run Without Foil

A dry run cycles the whole line at speed with no foil, to show that feeder, press, air ejection and stacker move in step before any of your foil is used.

Write the dry-run length into the test plan. A PMMI ProSource guide to packaging-machinery FATs recommends at least 24 hours of dry cycling.

Production Run at Contracted Speed

Run the line on your own foil at the line speed written in the contract, for the number of containers written in the test plan. On a foil container press, line speed is the synchronized speed of feeder, press and stacker together, which runs at 40 to 80 strokes per minute; a stroke figure quoted for the press alone is not the speed the line produces at.

The coils must be your production foil, the alloy, temper, gauge and lacquer you will actually buy, sent to the builder ahead of the test.

Specify the run as a number of containers rather than a number of hours, and agree it with the builder early, since that number sets how many coils you ship. During the run, log every stop and its cause, and compare the good containers counted at the stacker with the output per hour the contract states.

Formed Container Quality

Measure containers from the run against the container drawing in the contract, using calibrated instruments, and check them for the defects a foil press produces. Take samples at the start, middle and end of the run, and from every cavity of a multi-cavity mould.

  • Dimensions: length, width, depth and rim width within the tolerances on the drawing.
  • Walls: on wrinkle-wall containers, wrinkles evenly spaced around the wall; on smooth-wall containers, no wrinkles.
  • Rim: the curl complete and even all round; smooth-wall trays that will be heat-sealed with film or a foil lid need a flat, horizontal rim.
  • Pinholes: hold containers against a light in a dark area; light through a wall or corner is a hole.
  • Trimmed edge: no burrs or loose slivers of foil along the cut edge.
  • Stacking: containers nest and separate from the stack without sticking, and the counter’s stack count is right.

Mould Changeover

Have your own technicians change the mould, with the builder’s engineer beside them, and time it from the last good container off the old mould to the first good container off the new one.

Compare the measured time with the changeover time in the contract. If the contract gives none, record the time from the FAT as your baseline.

Fault Simulation and Restart

Simulate the faults you expect in production and check two things each time: the line stops safely and the HMI shows the cause, and it restarts only when an operator presses start. Build the list from the stoppages your plant actually has:

  • Foil break or coil end: the strip sensor stops the line.
  • Misfeed: a short or crooked feed is detected and the press stops.
  • Stacker jam: containers backing up at the stacker stop the line.
  • Air pressure drop: closing the air supply valve stops the line with an alarm.
  • Power loss: the main supply is cut during running, then restored.

Test the restart as two steps: release the emergency stop and confirm nothing moves, then press start.

When power returns after the cut, the line must not start by itself and the settings on the HMI should be unchanged. No moving part, including the press slide, may drop when the power goes or comes back.

Maintenance Access and Spare Parts

Check that routine maintenance can be done safely and quickly, and that the spare parts and tools you need ship with the line. Every lubrication and adjustment point should be reachable with the line stopped and from outside the guarded die area.

Ask the builder to change the wear parts the manual lists for frequent replacement while you time it.

Check the spare-parts list against the parts on the line: each entry should carry the builder’s part number and, for bought-in parts, the maker’s own part number. Count the start-up spares and special tools the contract lists before they are packed; anything missing goes on the punch list.

Documents to Collect Before Shipment

Collect the manuals, drawings, software and conformity papers at the FAT and check each against the line you have just tested:

  • Instruction manual: operation and maintenance instructions in the language of the country where the line will run, with the spare-parts list.
  • Drawings: as-built electrical and pneumatic schematics, and the mould drawings.
  • Software: a backup of the PLC program and the HMI recipes as they ran at the FAT.
  • Declaration of conformity: for the EU, the EC declaration of conformity, with each unit’s model and serial number matching its nameplate.

Under the EU Machinery Directive the risk assessment belongs to the technical file, which the builder must make available to national authorities, not to the buyer, so you receive a copy only if the purchase contract requires one.

The Machinery Regulation (EU) 2023/1230 replaces the Directive for lines placed on the EU market from 20 January 2027. A line arriving after that date needs its declaration issued under the Regulation.

Close the FAT with a signed report that lists every open item with an owner and a due date, and states whether the line ships accepted or conditionally accepted with those items open.